Before
After
Day1
Rip out
- Toilet to be removed
- Vanity, mirror, light fixture, sink and faucet to be removed
- Tile and drywall to be removed around tub
- Bulk head (aka drop ceiling) over tub area to be removed (If one exists)
- Baseboards, window casing and door casing to be removed
- Floor tile to be removed
Day2
Plumbing Rough in
- Re-locate drain to center of shower and install shower drain
- Install shower valve and rough in location for shower head or wall outlet
- Re-locate plumbing for sink drain and faucet supply lines to center of sink base
- Cap off all water supply lines so that tile, drywall or cabinetry can be neatly cut around pipes.
Day3
Electrical rough in
- Mount pot lights
- Mount exhaust fan
- Rough in electrical boxes for wall sconces
- Install new light switches
- Install new electrical receptacle (GFCI)
- Run dedicated line to electrical panel (if sufficient electrical is not present in existing bathroom)
Day4
Insulation, Prep. and Drywall
- Install new insulation and vapour barrier on outside shower wall
- Install new insulation and vapour barrier in ceiling above shower
- Repair holes in subfloor (from relocating shower drain)
- Rescrew entire subfloor
- (If necessary) Shim and/or plane down studs where new drywall is to be applied to ensure flat installation of new drywall.
- Install additional studs in ceiling above shower as well as where new drywall will meet up with old drywall (if currently not existing)
- Install new drywall on shower walls and ceiling
- Repair drywall where holes have been created during rip-out, electrical and/or plumbing rework
- Apply first coat of drywall compound
Day5
Drywall Continued
- Sand down first coat of drywall compound
- Apply second coat of drywall compound
Day6
Tile, Drywall continued
- Sand down second coat of drywall compound
- Apply final coat of drywall compound (if required) Use fast drying compound
- Prime bathroom
Day7
Paint
- Apply first coat of paint to bathroom
Day8
Build Shower, Floor prep
- Install sloped shower base (Schluter foam)
- Install shower curb
- Install waterproof membrane on shower base and walls up to the ceiling
- (if necessary) Feather out high and low spots on floor with cement to ensure flat application of floor tile
- Install Ditra uncoupling membrane on bathroom floor
Day9
Tile
- Start tiling bathroom
Day10
Tile Continued…
- Finish tile (including bathroom floor)
Day11
Grout
- Grout bathroom
- Install silicone
- Leave grout to dry
Day12
Vanity, Finish electrical, Measure for countertop
- Install vanity
- Install mirror
- Install baseboards, window casing and door casing
- Install light fixtures
- Install all electrical plates and trims for pot lights and fan
- Measure for custom countertop (approximately 2 weeks from time of measure to manufacture and install)
Day13
Measure for shower glass
- Measure for custom shower glass (approximately 2 weeks from time of measure to manufacture and install)
Day14
Paint
- Apply second coat of paint (if required)
- Paint baseboards, window casing and door casing
Day15
Countertop install, Finish plumbing (Aprox. 2 weeks after Day 12)
- Install countertop
- Install toilet
- Install shower trim plates and shower heads
- Install lavatory faucet and drain for sink
- Install bathroom accessories
Day16
Shower glass (Aprox. 2 weeks after Day 13)
-
Installation of shower glass
- Job is complete